Weekly Meetings for ME 492

Teams are working continuously toward completion of the design. Weekly meetings are held with project mentors. Each team is responsible for preparing a meeting agenda and providing the mentor with a rubric for evaluating the meeting. Use this Excel template to create a custom rubric for every meeting. (PDF version)

Refer to the more detailed explanation of the rubric.

Refer to the meeting toolbox web page for information on how to run effective meetings.

Assignments

  1. Team operating contract due 19 January 2018
  2. Project contract due 26 January 2018
  3. Concept Analysis due 2 March 2018
  4. Progress Presentations due Varying Dates
  5. Conceptual Design Progress Report due 21 March 2018